← Research In Progress

Infrastructure

Internet, power and cabling

Recommendation

Infrastructure Recommendation

Status

AMBER

Lightwire plan and all hardware are locked in. The cable run is planned for Easter 2026 but has not yet been executed, and two key checks remain outstanding before the configuration can be confirmed as complete.

Summary

The Max Storage infrastructure plan is built around Lightwire Fixed Wireless at $139/month as the primary internet connection, extended from the house to the shed via a 200m OS2 single-mode fibre cable run. All hardware needed for the cable run has already been purchased. The only remaining tasks before the shed has internet are to source alkathene conduit, book a mini-excavator, and complete the physical installation over Easter 2026.

The shed will be connected at gigabit speed via the OS2 fibre to the TP-Link ER706W router. The ER706W feeds a TP-Link TL-SG116P 16-port PoE+ switch, which powers and connects the cameras and NVR. The alarm communicator (DSC TL280E) connects to the ER706W on the management VLAN. No port forwarding is required -- camera remote access uses Hik-Connect P2P relay, and alarm management uses the DSC Connect cloud.

For Phase 1, no backup connectivity is recommended. All safety-critical systems (NVR recording, gate access via local credentials, alarm signalling via cellular) continue to operate independently if the internet drops. The only loss during a Lightwire outage is remote viewing and remote PIN management -- an accepted risk at Phase 1 with a small and known customer base. In Phase 2, a 4G mobile backup router (TP-Link MR6400, ~$200 hardware, ~$20/month SIM) is the recommended addition, bringing the total monthly cost to approximately $159. Starlink at $159/month is not recommended as a backup because its ongoing cost equals the entire Lightwire primary plan cost and is difficult to justify when only remote visibility is at stake.

Phase 1: Lightwire + Cable Run

Primary connection:

Lightwire Fixed Wireless Unlimited -- $139/month (24-month contract, locked in).

Cable run -- Easter 2026:

All hardware is already purchased. Remaining work is conduit procurement and physical installation.

ItemEstimated cost (NZD incl. GST)
Alkathene conduit (2 x 100m rolls, 25mm)$260-$320
Conduit gland/fitting sets (x2 ends)$40-$80
Mini-excavator hire (half day)$400-$600
Reinstatement materials (topsoil, seed)$50-$100
Total remaining cable run cost~$750-$1,100

Hardware already purchased (sunk costs, not included above): 200m OS2 fibre drum, StarTech SFPGLCLHSMST SFP module, TP-Link MC210CS media converter, Dynamix LC-SC patch lead, TP-Link TL-SG116P PoE+ switch, TP-Link ER706W router.

Phase 2: 4G Backup Connectivity

Recommended backup option:

TP-Link MR6400 or MR6500v 4G router connected to the ER706W WAN2 port, with a Spark Business IoT SIM or One NZ equivalent (~$20/month). The ER706W supports automatic WAN failover -- no manual action is needed when Lightwire drops.

Combined monthly cost: Lightwire $139 + 4G SIM $20 = $159/month.

Before committing to 4G backup, confirm that adequate signal is available at the shed. See open actions below.

Key Open Actions

  1. Peak-hour speed test (before launch) -- Run a speed test from the Lightwire connection at the house during the 3pm-10pm window on a weekday. Upload must be consistently at or above 3.5 Mbps. If it regularly drops below 3 Mbps, H.265 camera sub-stream quality will be degraded and Lightwire should be contacted about congestion management or a plan upgrade. This is the single most important pre-launch technical check.
  1. 4G coverage check at the shed -- Walk the shed site with a Spark SIM and a One NZ SIM and record signal strength. Three or more bars of 4G inside or adjacent to the shed is the minimum for Option B backup to be viable. If coverage is inadequate, Starlink should be reconsidered for Phase 2.
  1. Conduit procurement before Easter 2026 -- Two rolls of 25mm x 100m alkathene poly pipe from Farmlands Rotorua (Te Ngae Road) or RD1 Rotorua. Phone ahead to confirm stock.
  1. Lightwire CPE port confirmation -- Confirm which LAN port on the Lightwire CPE router at the house the MC210CS media converter should plug into, and that the CPE supports gigabit ethernet on its LAN ports.
Options Considered Vendor and product options with costs and trade-offs

Infrastructure Options

Status

AMBER

Primary plan is locked in. Backup connectivity option is identified but not yet committed, pending coverage check at the shed.

Primary Internet (Locked In -- Not Subject to Selection)

Lightwire Fixed Wireless Unlimited

ParameterDetail
ProviderLightwire Business/Rural
TechnologyFixed wireless (FWA)
Download speed20-70 Mbps typical; 10 Mbps guaranteed peak
Upload speed~5 Mbps typical (not speed-guaranteed)
Monthly cost$139/month (24-month contract)
Data capUnlimited
HardwareLightwire CPE at house (already installed/contracted)
Backhaul to shedOS2 fibre cable run (hardware purchased; installation Easter 2026)

The Lightwire plan meets the site bandwidth requirement (5 Mbps sustained upload, 10 Mbps download). The upload margin is thin -- worst-case concurrent demand is ~3.5 Mbps against ~5 Mbps typical upload. A peak-hour speed test is required before launch to confirm this holds under real conditions.


Backup Connectivity Options

The following options address backup/failover only. The primary Lightwire plan is not subject to selection.

What it provides:

Satellite broadband connected to the ER706W second WAN port. Cold standby -- Starlink remains connected, ER706W fails over automatically when Lightwire drops.

ItemCost (NZD incl. GST)
Starlink Standard hardware kit~$599 one-time
Monthly plan -- Residential Standard$159/month
Total combined monthly (with Lightwire)$298/month
Year 1 total cost (hardware + 12 months)~$2,507

Upload performance:

5-25 Mbps typical. Sufficient for H.265 sub-stream remote view (0.5-1 Mbps) during a Lightwire outage.

Pros:

  • High and consistent upload -- best backup quality
  • No tower congestion (satellite)
  • Self-install; no technician visit needed
  • ER706W failover is automatic

Cons:

  • $159/month ongoing for a link used only during rare Lightwire outages
  • $599 upfront hardware cost
  • Requires unobstructed sky view from shed -- obstruction check needed
  • Residential terms may not permit commercial use; Starlink Business plan (~$229/month) may be required
  • Adds ~$1,908/year for a backup protecting only remote visibility

Verdict: Not recommended unless 4G coverage at the shed proves inadequate.


Option B: 4G/5G Mobile Backup Router

What it provides:

A 4G cellular router connected to the ER706W WAN2 ethernet port. Low-cost backup for alarm heartbeats, brief remote management, and occasional remote camera sub-stream access.

Coverage at Hamurana:

Hamurana is on the northwest shore of Lake Rotorua, approximately 15km from Rotorua city. Spark and One NZ provide 4G coverage to most Rotorua lakeside areas, but signal at Te Waerenga Road specifically is at the edge of rural coverage and requires on-site confirmation before committing to this option.

Recommended hardware:

HardwareCost (NZD incl. GST)Notes
TP-Link MR6400 or MR6500v$180-$250Matches existing TP-Link ecosystem; available at PB Tech, Noel Leeming
Huawei B818$350-$450Better rural antenna performance; higher cost
GL.iNet GL-X3000 (5G)$450-$600Future-proof; overkill for backup use

Recommended: TP-Link MR6400/MR6500v.

SIM and plan options:

ProviderPlan typeMonthly cost (NZD incl. GST)Data
Spark Business IoT SIMMachine-to-machine, always-on~$15-$25/monthLow data
Spark Prepay 4GTopped up monthly~$15-$20/month2GB
One NZ (Vodafone)Prepay or light data~$15-$20/month2GB
2degreesData SIM~$10-$15/month1-2GB

Recommended SIM: Spark Business IoT SIM or One NZ equivalent. These are designed for always-on devices and avoid the inactive SIM deactivation risk that prepay SIMs carry after 90 days without use.

Total combined monthly cost (Lightwire + 4G SIM): ~$159/month.

Upload speed on rural 4G: 2-10 Mbps typical. Sufficient for alarm heartbeats and brief remote management sessions. H.265 sub-stream remote view (0.5-1 Mbps) will work at 3+ bars signal.

Pros:

  • Very low monthly cost vs Option A: Starlink
  • No upfront hardware cost beyond the router (~$180-$250)
  • No sky-view obstruction issues
  • TP-Link hardware integrates cleanly with existing Omada ecosystem
  • No commercial use restrictions

Cons:

  • Coverage at Hamurana is unconfirmed -- must verify on-site before committing
  • Upload speeds lower and more variable than Starlink
  • Rural 4G may itself be congested at peak hours
  • Requires on-site signal test before purchasing hardware

Verdict: Recommended for Phase 2 if coverage check passes.


Option C: No Backup — Phase 1 Risk Acceptance

What this means:

Accept Lightwire as the sole internet path at launch. If Lightwire goes down, remote visibility is lost until it recovers.

Operational impact during a Lightwire outage:

SystemBehaviour during outageOperational impact
NVR / camerasContinues recording locally to on-site storageNone -- footage preserved
Gate / access controlOperates on locally stored PIN codesNone -- customer access unaffected
DSC TL280E alarmAutomatically fails over to cellular pathNone -- alarm remains functional
Hik-Connect remote viewUnavailableCannot remotely view cameras
Remote PIN managementUnavailableCannot add or remove access codes remotely
DSC Connect appAlert delivery continues via alarm cellular pathMinimal

Lightwire reliability context:

99.9% claimed uptime equates to less than 9 hours of unplanned outage per year. Lightwire towers have backup power generation, reducing extended outage risk from local power cuts.

Pros:

  • Zero additional cost
  • Simplest network configuration
  • All safety-critical functions remain operational during outages

Cons:

  • Remote visibility lost during outages
  • Cannot review camera footage remotely during an incident until connectivity recovers
  • Phase 2 upgrade requires revisiting router configuration (minor)

Verdict: Appropriate for Phase 1 given low customer volume and all safety-critical systems operating independently.


Cable Run Options

Underground OS2 Fibre (Selected -- Hardware Purchased)

200m pre-terminated LC-LC OS2 single-mode fibre buried in alkathene conduit across the paddock. No field splicing -- plug-and-play once conduit is in the ground.

Conduit sourcing:

SupplierProductApproximate price (NZD incl. GST)
Farmlands (Te Ngae Road, Rotorua)25mm x 100m alkathene poly pipe$120-$160/roll
RD1 Rotorua25mm x 100m alkathene$120-$155/roll
Placemakers20mm sub-duct, 100m coil$90-$130/roll

Recommendation: Two rolls of 25mm blue alkathene -- one per 100m of the run. Pull a spare draw-wire through a second conduit if the trench is being dug anyway (enables future cable addition without re-trenching).

Trench depth: Minimum 300mm under paddock. 450mm under any vehicle track or farm machinery crossing.

Installation notes:

  • The fibre is pre-terminated LC-LC -- do not cut or strip the cable
  • Pull using a draw-wire with a cable sock or pulling grip; do not tape to the connector
  • Minimum bend radius: 30mm installed, 15mm during installation -- use swept elbows at conduit entry points
  • Label both ends at installation: "OS2 FIBRE -- HOUSE TO SHED -- DO NOT BEND SHARPLY"
  • Test with a ping from the shed router to the house before closing the trench

Total remaining cost (conduit + labour only; hardware already purchased):

ItemEstimated cost (NZD incl. GST)
Alkathene conduit (2 x 100m rolls)$260-$320
Gland/fitting sets (x2 ends)$40-$80
Mini-excavator hire (half day)$400-$600
Reinstatement (topsoil, seed)$50-$100
Total~$750-$1,100
Cross-System Requirements How this area interacts with other systems and constraints

Infrastructure Integration

Status

AMBER

Integration design is complete and all hardware is selected. Cable run not yet executed; integration points will be confirmed live at Easter 2026.

How Infrastructure Connects to Other Systems

Cameras (Hik-Connect P2P)

The Hikvision NVR and cameras sit on VLAN 10. The NVR registers with Hik-Connect -- Hikvision's cloud relay service. Remote live-view and playback reach Ed and Tom via the Hik-Connect app or iVMS-4200 desktop client without any port forwarding or static IP address.

The NVR requires outbound internet access to Hik-Connect relay servers (TCP 80, 443, and Hik-Connect-specific ports including 8000, 8200, and 554 for RTSP). The ER706W firewall should allow these outbound connections from VLAN 10 and deny all inbound connections from the internet to the camera VLAN. No direct internet exposure of any camera or the NVR is required or recommended.

If the internet drops, the NVR continues recording locally. Hik-Connect remote view is unavailable until connectivity is restored -- this is an accepted Phase 1 risk.

Alarms (DSC TL280E with Cellular Fallback)

The DSC TL280E alarm communicator sits on VLAN 20 (management). It uses the internet path to send heartbeats and alarm events to the DSC cloud and the monitoring centre. If the IP path drops, the TL280E must automatically fail over to its own cellular SIM for alarm signalling -- this is a mandatory requirement, not a nice-to-have.

Note: the TL280E is ethernet-only. It does not itself include a cellular radio. A separate DSC GS150 cellular communicator (or replacement with the DSC TL2803GR combo unit) is required to achieve the Grade 3 dual-path target. This is an open decision for Ed -- see the alarms area documentation.

The ER706W router being on UPS is important here: during a brief power outage at the shed, keeping the router online delays the point at which the alarm communicator loses its IP path and triggers the cellular fallback. This reduces unnecessary cellular-path alarm traffic during short power cuts.

Access Control (Remote Management via ER706W)

The access control panel (Phase 2) will sit on VLAN 20 alongside the alarm communicator. Remote management -- adding or removing customer PIN codes -- requires an internet connection. During a Lightwire outage, remote PIN management is unavailable.

The gate pin pad and Merlin opener motors must continue operating on locally stored credentials regardless of internet state. No internet dependency is permitted for customer access.

The ER706W management interface is accessible remotely via the TP-Link Omada cloud controller -- no separate VPN is required for Phase 1 or Phase 2 router management. If direct LAN-level access is ever needed, the Omada controller provides it.


VLAN Topology

The ER706W supports VLAN segmentation and inter-VLAN firewall rules. The recommended topology separates camera traffic from management and alarm traffic.


Lightwire (house) -> MC210CS media converter -> OS2 fibre -> ER706W (shed)

  ER706W LAN port 1 -> TL-SG116P PoE switch (VLAN 10: cameras)
    TL-SG116P -> Hikvision NVR
    TL-SG116P -> IP cameras (via NVR built-in PoE ports or direct switch ports)

  ER706W LAN port 2 -> DSC TL280E alarm communicator (VLAN 20: management)
  ER706W LAN port 3 -> access control panel (VLAN 20: management, Phase 2)
  ER706W WiFi -> operator use (VLAN 20: management)

VLAN 10 -- Camera network:

  • Members: NVR, IP cameras
  • Outbound allowed: Hik-Connect relay servers (TCP 80, 443, 8000, 8200, 554)
  • Inbound from VLAN 20: denied
  • Lateral movement between cameras: denied (cameras must not reach each other's management interfaces)
  • NVR to camera access: allowed (required for NVR to pull streams)

VLAN 20 -- Management network:

  • Members: DSC TL280E communicator, access control panel, operator devices on-site
  • Outbound allowed: DSC Connect cloud servers, access control cloud service, general internet for management
  • Inbound from VLAN 10: denied

Router hardening (required before deployment):

  • Change default admin password on ER706W
  • Change default passwords on TL-SG116P switch
  • Change default passwords on all cameras and NVR
  • Disable UPnP on ER706W
  • Disable remote management on ER706W web UI (use Omada cloud instead)
  • Enable firewall logging on ER706W for incident investigation

WAN Failover Configuration (Phase 2)

When a 4G backup router is added in Phase 2, the ER706W should be configured as follows:

  • WAN1: Lightwire (OS2 fibre via MC210CS into ER706W SFP WAN port)
  • WAN2: 4G router LAN ethernet into ER706W WAN2 ethernet port
  • Mode: Failover only -- NOT load balancing. Camera and alarm traffic must not be split across both links simultaneously.
  • Health check: Configure ER706W to ping 8.8.8.8 and 1.1.1.1 on both WAN links. Failover triggers automatically when WAN1 health check fails.

If Starlink is added instead of 4G (see options document), the Starlink dish connects to WAN2 the same way via ethernet. Starlink Gen 3 hardware supports bridge mode to disable the Starlink router's NAT -- confirm the generation before configuring.


UPS Requirements for Router

The ER706W router must be on UPS to maintain the alarm communicator IP path during brief power outages.

Rationale: The DSC TL280E uses the IP path as its primary alarm signalling route. If the router loses power and the IP path drops, the TL280E immediately begins cellular fallback procedures. Keeping the router online during short outages (the most common type) delays this transition and reduces unnecessary cellular alarm traffic.

UPS specification (minimum for all shed IT equipment):

DeviceLoad with headroom
TP-Link ER706W router18W
TP-Link TL-SG116P switch12W
Hikvision NVR36W
DSC HS2032 alarm panel18W
Total84W
  • Type: Line-interactive with automatic voltage regulation (AVR) -- handles the voltage sags common on rural power networks without switching to battery unnecessarily
  • Output waveform: Pure sine wave (required for NVR HDD motors)
  • VA rating: 1000 VA / 600W minimum (allows for future load growth without replacement)
  • Runtime at 84W (no cameras on UPS): approximately 45-60 minutes
  • Runtime at 127W (cameras included on UPS): approximately 25-35 minutes

The DSC HS2032 alarm panel has its own internal sealed lead-acid battery rated for 4+ hours standby. It does not depend on the UPS for extended operation and is included in the load calculation above only for Phase 1 completeness.

Legal & Technical Requirements Regulatory obligations and technical standards that constrain options

Infrastructure Requirements

Status

AMBER

Requirements are fully documented. Hardware is purchased and plan is locked in. Cable run not yet executed.

Hardware Already Purchased

All of the following items are on-hand and ready for the Easter 2026 installation:

ItemDetailCost paid (NZD incl. GST)
OS2 fibre cable200m 6-core LC-LC pre-terminated on drum (Apollo Technology AU, INV-8976)AUD $579.08
TP-Link MC210CSSC-port gigabit media converter (house end)$51.21
Dynamix FSM-LCSC-1LC-SC patch lead 1m (house end adapter)$10.04
StarTech SFPGLCLHSMST1000BASE-LX LC SFP transceiver module (shed end)$89.52
TP-Link TL-SG116P16-port PoE+ gigabit switch (shed)$217.98
TP-Link ER706WOmada Multi-WAN VPN router (shed)Purchased

Still to procure before Easter 2026: alkathene conduit (2 x 100m rolls, 25mm) from Farmlands or RD1 Rotorua.


Bandwidth Requirements

The site uses a local NVR architecture. Cameras record to on-site storage; internet bandwidth is consumed only by remote live-view sessions and motion-event clip uploads.

Codec requirement: H.265 is mandatory on all cameras. H.264 would approximately double the live-view sub-stream bandwidth and could push concurrent upload demand above the Lightwire ceiling. This is a disqualifying criterion for camera selection.

Upload consumption model:

SystemUpload (Mbps)Notes
CCTV remote live-view (1 camera sub-stream)0.5-1.0Via Hik-Connect relay; single concurrent viewer assumed
CCTV motion-clip upload bursts0.5-2.0 peakShort bursts on motion events; not continuous
Alarm communicator heartbeat0.1DSC TL280E to monitoring centre
Access control remote management0.1Negligible
General overhead0.3Firmware updates scheduled off-peak
Total worst case (burst)~3.5
Total typical concurrent~1.0-1.5Well within Lightwire ~5 Mbps upload

Minimum plan requirement: 5 Mbps sustained upload, 10 Mbps download minimum. The Lightwire Unlimited plan meets this under typical conditions. Upload is not speed-guaranteed -- a peak-hour speed test is required before launch.

Why continuous cloud upload is not used: Continuous upload of 4 cameras at 4MP H.265 would require approximately 6 Mbps upload, exceeding the Lightwire ceiling. NVR local-recording architecture avoids this entirely.


VLAN Separation Requirement

Two separate network segments are required. Mixing camera traffic with alarm and management traffic is not acceptable due to the security risk of Chinese-manufactured camera hardware with known firmware vulnerability history.

VLANPurposeMembers
VLAN 10 -- CameraCamera and NVR trafficHikvision NVR, IP cameras
VLAN 20 -- ManagementAlarm and operations trafficDSC TL280E, access control panel, operator devices

Inter-VLAN traffic must be blocked at the ER706W. Cameras must not be able to initiate connections to management devices.


Offline Operation Requirements

These requirements are mandatory -- they are not relaxable at any phase.

SystemRequired offline behaviour
NVRMust continue recording to on-site storage with no internet dependency
Gate / access controlMust operate on locally stored PIN credentials -- internet loss must not lock out customers
DSC TL280E alarmMust fail over to cellular path automatically when IP path fails
Remote live-viewWill be unavailable during outage -- this is explicitly accepted
Remote PIN managementWill be unavailable during outage -- accepted for Phase 1

UPS Specification

Required protection: The NVR, PoE switch (to keep cameras recording), and router (to maintain alarm IP path) must remain powered during brief outages.

DeviceLoad with headroom
TP-Link ER706W router18W
TP-Link TL-SG116P switch12W
Hikvision NVR36W
DSC HS2032 alarm panel18W
Total without cameras84W
With 4x cameras on PoE (optional)127W

Minimum specification:

  • Type: Line-interactive with AVR (not standby/offline -- AVR required for rural voltage sags)
  • Output waveform: Pure sine wave (required for NVR HDD motors)
  • VA rating: 1000 VA / 600W minimum
  • Runtime at 84W: approximately 45-60 minutes
  • Runtime at 127W: approximately 25-35 minutes

The DSC HS2032 alarm panel has its own internal sealed lead-acid battery (4+ hours standby) and is independent of the UPS. Do not remove or downsize this internal battery.

Rural power outages at this location may be longer than the urban norm. A 1500 VA / 900W unit would extend runtime to approximately 40-55 minutes at full load and is recommended if budget allows.


Power Circuit Requirements

A dedicated 10A general-purpose circuit is required at the shed for the IT and security equipment. This circuit must not be shared with roller door opener motors (motor load switching introduces voltage spikes that can damage sensitive electronics).

A licensed electrician must install this circuit in compliance with AS/NZS 3000:2018 (Wiring Rules). The fibre cable from the house is inherently electrically isolated (no metallic signal conductors), which eliminates ground loop risk. The steel armouring of the fibre cable must be earthed at the shed end only.


Cabling Requirements

House-to-shed inter-building link:

200m OS2 LC-LC single-mode fibre buried in alkathene conduit. Minimum burial depth 300mm under paddock, 450mm under vehicle tracks. Cable must run inside conduit throughout the underground section for rodent protection and future replaceability. Leave a draw-wire in the conduit after installation.

Intra-shed camera cabling:

Cat6 UTP or FTP (shielded preferred in metal shed environment) for PoE camera runs. Conduit must be run to every planned camera position at initial installation -- retrofitting conduit after fit-out is significantly more expensive. Runs are well under 100m per camera; no powered extenders required.

PoE standard: 802.3af (15.4W per port) is sufficient for Hikvision 4MP cameras (6-9W draw). The TL-SG116P supports 802.3at (PoE+, 30W per port), providing headroom for higher-draw hardware in future.


Standards and Compliance

StandardRelevance
AS/NZS 3000:2018Low-voltage electrical installations (power circuit to IT cabinet)
AS/NZS 3080:2013Telecommunications installations in buildings (Cat6 data cabling)
AS/NZS 2201.1:2007Intruder alarm systems (DSC alarm panel installation and earthing)
NZS 4512:2021Fire detection and alarm systems (relevant only if alarm panel is connected to fire detection in future)
Raw Research Detail Full Tier 3 agent outputs — model-by-model specs, all options assessed, sourcing notes

Internet Connectivity Options

Executive Summary

AreaCritical finding
Phase 1 internetLightwire fixed wireless at $139/month is locked in and adequate — no backup is needed at launch because the alarm, gate, and cameras all continue working independently if the internet drops.
Cable run (Easter 2026)Hardware already purchased; remaining cost is ~$750–1,100 for conduit and labour (digger + two people for a half day to bury 200m of conduit across the paddock).
Most important check before launchRun a Lightwire speed test during peak evening hours (3–10pm) — upload should be consistently above 3.5 Mbps; if it drops below that, H.265 camera streaming will be degraded and you need to talk to Lightwire.
Phase 2 backup recommendationAdd a 4G mobile router (TP-Link MR6400, ~$200) with a Spark or One NZ IoT SIM (~$20/month) — total monthly cost becomes $159; first confirm 4G signal strength at the shed with a mobile phone.
Starlink — not recommendedAt $159/month it costs as much as the primary Lightwire plan just to back up remote viewing; only reconsider if 4G coverage at the shed turns out to be inadequate.
What goes offline if internet dropsOnly remote camera viewing and remote PIN management — everything that actually matters (alarm, gate access, NVR recording) keeps working independently.

Requirements Loaded

Source: Compound requirements document knowledge/integration/security-infrastructure.md (last-updated: 2026-04-01) — POPULATED.

Key constraints extracted:

ConstraintDetail
Minimum upload5 Mbps sustained
Minimum download10 Mbps
Worst-case burst upload~3.5 Mbps (concurrent live-view + clip upload + alarm + access control + overhead)
Typical concurrent upload~1.0–1.5 Mbps
Codec requirementH.265 mandatory — H.264 would approximately double upstream demand and could breach the 5 Mbps ceiling
NVR offline behaviourMust continue recording locally with no cloud dependency
Gate/access control offlineMust operate on locally stored credentials — no internet required for customer access
Alarm offlineMust fail over to cellular path (DSC TL280E) automatically — IP path loss is acceptable
Remote visibility offlineUnavailable during outage — explicitly accepted
UPS requirementRouter (ER706W, ~15W) must be on UPS to maintain IP path and delay cellular alarm failover during brief power outages
Primary ISPLightwire Fixed Wireless — LOCKED IN at $139/month (24-month Unlimited plan)
Hardware already purchasedER706W router, TL-SG116P PoE+ switch, MC210CS media converter, 200m OS2 fibre, StarTech SFP, LC-SC patch lead
Cable run timingEaster 2026 — materials already on hand

Phase 1 Budget: ~$3,000 (cable run + installation + plan)

Status of budget envelope: The hardware for the cable run (200m OS2 fibre, SFP, media converter, LC-SC adapters) is already purchased and therefore already sunk. The Lightwire plan at $139/month is contracted. The primary remaining cost items within the $3,000 envelope are:

  • Labour for the Easter 2026 cable run (conduit, penetrations, termination)
  • Alkathene conduit (not yet purchased)
  • Any backup connectivity hardware (if Phase 1)
  • Lightwire installation/activation fee (if any — see Open Questions)

The $3,000 envelope is therefore largely consumed by the cable run labour + conduit + ongoing Lightwire plan costs. Backup connectivity should be treated as a Phase 1 stretch or Phase 2 item depending on the option chosen.

Cable Run to Shed

Already decided and partially executed. Materials on hand:

ItemDetail
Cable200m 6-core OS2 LC-LC pre-terminated single-mode fibre on drum
House endTP-Link MC210CS SC-port gigabit media converter + Dynamix FSM-LCSC-1 LC-SC patch lead (converts OS2 LC to SC for the MC210CS)
Shed endStarTech SFPGLCLHSMST 1000BASE-LX LC SFP transceiver module in ER706W WAN/LAN port
Distance~200m — well within OS2 single-mode range (rated to 10km at 1310nm)

OS2 single-mode is the correct choice for this run. OS1/OS2 single-mode has no distance or attenuation concerns at 200m. Multimode would have been adequate at this distance but OS2 future-proofs the run.

Cable run installation considerations (Easter 2026):

The fibre is pre-terminated LC-LC. The MC210CS at the house end requires SC, which the Dynamix LC-SC patch lead handles. No field splicing is required — this is a plug-and-play run once conduit is in.

Conduit requirement:

  • Route from house/main building to shed: ~200m estimated
  • Underground burial recommended for the majority of the run (protects fibre from UV degradation, physical damage, and stock)
  • Fibre is fragile relative to copper — do not pull it through conduit with sharp bends; minimum bend radius for OS2 is typically 30mm (check drum label)
  • Alkathene conduit (polyethylene water pipe, 20mm or 25mm ID) is the standard NZ rural approach for underground cable protection and is available at rural merchants

Alkathene conduit NZ pricing (as at early 2026):

Alkathene is sold in rolls at Farmlands, RD1, and Placemakers. Approximate pricing for 25mm OD alkathene (suitable for single fibre cable):

SupplierProductApproximate price (NZD incl. GST)
Farmlands25mm x 100m poly pipe (blue or black)$120–$160/roll
RD125mm x 100m alkathene$120–$155/roll
Placemakers20mm conduit/sub-duct, 100m coil$90–$130/roll

Recommendation: Purchase one 100m roll of 25mm blue alkathene and one 100m roll of 20mm sub-duct, or two 100m rolls of 25mm — total ~$250–$320 NZD. If the trench is being dug anyway, pull a spare draw-wire through a second conduit for future cabling.

Penetration points:

  • Use a 25mm gland or conduit entry fitting at both the house wall penetration and the shed wall penetration
  • Seal penetrations with expanding foam (fire-rated if passing through a fire-rated wall) and/or silicone
  • Label both ends of the fibre at installation time

Trench depth: Minimum 300mm cover under paddock/lawn. 450mm under any vehicle track.

Estimated labour cost: A half-day digger hire (mini-excavator) plus two people for a 200m trench run and reinstatement: approximately $600–$1,200 depending on ground conditions and whether Ed/Connor can assist. Fibre termination is plug-and-play (pre-terminated cable) — no specialist splicing labour required.

Total cable run cost estimate (conduit + labour, hardware already purchased):

ItemEstimated cost (NZD incl. GST)
Alkathene conduit (2 x 100m rolls)$260–$320
Gland/fitting sets (x2 ends)$40–$80
Mini-excavator hire (half day)$400–$600
Reinstatement materials (topsoil, lawn seed)$50–$100
Total cable run (excl. already-purchased hardware)$750–$1,100

Lightwire Plan Validation Against Requirements

Plan: Lightwire Fixed Wireless Unlimited, $139/month, 24-month contract.

Claimed speeds: 20–70 Mbps download typical; 10 Mbps guaranteed peak download; ~5 Mbps upload typical.

Requirement: 5 Mbps sustained upload, 10 Mbps download minimum.

Assessment:

RequirementLightwire UnlimitedVerdict
5 Mbps sustained upload~5 Mbps typical upload (not guaranteed)MARGINAL — meets requirement under typical conditions; upload is not speed-guaranteed on this plan
10 Mbps download10 Mbps guaranteed peak; 20–70 Mbps typicalPASS
Data capUnlimited plan — no data capPASS
Fair use / throttlingLightwire Unlimited plans do not publish a fair use policy for residential/rural fixed wireless; verify with Lightwire at activationVERIFY
24-month pricing$139/month is the current Lightwire rural Unlimited rate; competitive for fixed wireless in the Rotorua/Waikato regionPASS
H.265 3.5 Mbps burstFits within ~5 Mbps upload; no headroom for simultaneous large uploads (e.g. NVR backup to cloud)PASS — provided no additional upload consumers are added

Key risk: Upload speed is listed as "typical" (~5 Mbps), not guaranteed. During peak evening hours (3pm–10pm), rural fixed wireless towers can experience congestion. The compound requirements mandate a real-load upload speed test at peak hours before confirming the plan meets the H.265 streaming requirement. This is flagged as Open Question 1 in the compound requirements and remains unresolved.

Conclusion: The Lightwire plan is locked in and cannot be changed. It meets requirements under typical conditions. The upload margin is thin — 3.5 Mbps worst-case demand against ~5 Mbps typical upload. Confirm with a speed test; if peak-hour upload drops to 3 Mbps or below the camera sub-stream will be degraded. The mitigation is to ensure H.265 is configured on the NVR (not H.264) and remote live-view is limited to one sub-stream at a time.

Connectivity Plan Options

Primary Plan (locked in — not subject to selection)

Lightwire Fixed Wireless Unlimited

  • Provider: Lightwire Business/Rural
  • Speed: 20–70 Mbps download / ~5 Mbps upload typical
  • Monthly cost: $139/month (24-month contract)
  • Hardware: Lightwire CPE unit at house (already installed/contracted)
  • Fibre backhaul to shed: via OS2 single-mode cable run (hardware purchased)

This plan is not optional. The following options address backup/failover connectivity only.

What it provides:

Satellite broadband. Connects to the ER706W second WAN port. Used only when Lightwire is down. Cold standby: Starlink dish powers up and remains connected; ER706W fails over automatically.

Current NZ pricing (early 2026):

ItemCost (NZD incl. GST)
Starlink Standard hardware kit (dish + router)~$599 one-time (standard residential)
Monthly plan — Residential Standard$159/month
Total Year 1 cost$599 + ($159 x 12) = $2,507

Note: Starlink hardware pricing in NZ has fluctuated. Check starlink.com/nz for current pricing before purchase. The $599 hardware cost is approximate as at early 2026.

Upload performance:

Starlink Residential Standard delivers 5–25 Mbps upload typical in NZ. This is sufficient for H.265 remote live-view (0.5–1 Mbps) and alarm/access management traffic during a Lightwire outage. Latency is 20–60ms — adequate for remote management; not ideal for real-time video but acceptable for backup use.

Self-install complexity:

Low. Starlink Standard kit is designed for self-install: position dish with clear sky view, run cable to router, connect to ER706W WAN2 port via ethernet. The ER706W supports load balancing and failover on WAN2 — configure as failover-only (not load balancing) to avoid routing camera traffic over both links simultaneously.

ER706W WAN failover compatibility:

The TP-Link ER706W Omada router has two WAN ports and supports automatic failover. Starlink connects to WAN2 via ethernet (Starlink router in bridge/bypass mode, or using the ER706W directly — note: Starlink's standard dish uses its own router; bridge mode is available on Gen 3 hardware but may require disabling Starlink's NAT). Confirm Starlink generation before configuring.

What falls back to Starlink during a Lightwire outage:

  • Remote camera live-view (Hik-Connect P2P) — available again via Starlink within ~30–60 seconds of failover
  • Alarm communicator IP path (DSC TL280E) — maintained; cellular fallback on alarm panel is not triggered if Starlink WAN2 is up
  • Remote management of access control and router

What does NOT use Starlink (alarm panel independent path):

The DSC TL280E alarm communicator has its own cellular SIM for alarm signalling. Alarm notifications to a monitoring station or DSC Connect app will route via cellular regardless of whether Starlink is in use. Starlink backup does not affect alarm cellular independence — the cellular path is always available whether Starlink is on or off.

Pros:

  • High and consistent upload speeds — better backup quality than rural 4G
  • No tower congestion at this location (satellite)
  • Self-install; no site visit required by technician
  • Provides genuine redundancy against Lightwire tower failure, power failure to tower, or fibre backhaul cuts
  • ER706W failover is automatic and transparent to all connected systems

Cons:

  • $159/month ongoing for a backup link that may be needed rarely (Lightwire reliability is 99.9%+ claimed)
  • $599 upfront hardware cost
  • Requires unobstructed sky view from shed or adjacent mounting point — obstruction check required (trees, shed roof geometry)
  • Starlink residential terms prohibit commercial use at some tiers — verify business vs residential plan terms; for a security monitoring application this is a grey area. Starlink Business plan (~$229/month) provides SLA and commercial use rights if this is a concern.
  • Adds ~$1,908/year in ongoing cost for a link that is rarely used

Option B: 4G/5G Mobile Backup Router

What it provides:

A cellular modem/router (USB stick in ER706W WAN2 USB port, or a standalone 4G router on WAN2 ethernet) providing mobile broadband backup when Lightwire is down.

Coverage at Hamurana, Rotorua:

Hamurana is a rural locality on the northwest shore of Lake Rotorua, approximately 15km northwest of Rotorua city centre. 4G coverage in this area:

  • Spark: Provides 4G coverage to most of the Rotorua lakeside areas including Hamurana according to Spark's published rural coverage maps. Signal at Te Waerenga Road specifically requires on-site confirmation — the area is at the edge of rural coverage.
  • Vodafone (One NZ): Similar coverage footprint to Spark in the Rotorua rural zone. Hamurana is likely marginal.
  • 2degrees: More limited rural coverage in this region; likely less reliable at Hamurana than Spark or One NZ.

Coverage verification is essential before committing to this option. The compound requirements flag this as Open Question 2 — a coverage map check and ideally an on-site mobile signal test are required. Without confirmed 4G signal at the shed, this option cannot be guaranteed to work.

Suitable hardware options:

OptionHardwareCost (NZD incl. GST)Notes
TP-Link TL-MR6500v or MR6400 4G LTE routerStandalone router connecting to ER706W WAN2 via ethernet$180–$250Simple setup; TP-Link ecosystem matches existing hardware
Huawei B818 4G/LTE routerStandalone; ethernet out to ER706W$350–$450Better antenna, good rural performance
ER706W USB modem portInsert compatible 4G USB dongle into ER706W$60–$120 (dongle)Dependent on ER706W USB modem compatibility list — verify before purchase
GL.iNet GL-X3000 (5G NR)5G-capable with fallback to 4G; ethernet out$450–$600Future-proof if 5G reaches Hamurana; overkill for backup use

Recommended hardware: TP-Link MR6400 or MR6500v — matches existing TP-Link/Omada ecosystem, straightforward setup, readily available in NZ (PB Tech, Noel Leeming, Spark Business).

SIM and plan options:

The backup link carries very low data: alarm heartbeats (~0.1 Mbps when active), brief remote management sessions, and alert notifications. This is a low-data backup application.

ProviderPlanMonthly cost (NZD incl. GST)DataNotes
SparkSpark Prepay 4G (topped up monthly)~$15–20/month for 2GB2GBLow commitment; top up as needed
One NZ (Vodafone)Prepay or light data plan~$15–20/month2GBSimilar to Spark
2degrees2degrees data SIM~$10–15/month1–2GBLower cost; coverage risk at Hamurana
Spark Business IoT SIMMachine-to-machine SIM for always-on devices~$15–25/monthLow dataDesigned for alarm/monitoring devices; stable long-term pricing

A Spark Business IoT SIM or One NZ equivalent is the most appropriate product for a device that sits connected 24/7 but uses little data. These avoid the "inactive SIM" risk that prepay SIMs can have (prepay SIMs may deactivate after 90 days without top-up if no data is used).

Upload speed on rural 4G:

Rural 4G at the edge of coverage typically delivers 5–20 Mbps download, 2–10 Mbps upload. Upload will be sufficient for alarm heartbeats and brief remote management. H.265 live-view remote access (0.5–1 Mbps sub-stream) will work if signal is at least 2 bars. Coverage must be verified on-site.

What falls back to 4G:

Same as Starlink Option A: Hik-Connect remote view, alarm IP path (reducing cellular alarm traffic), remote management.

What does NOT use 4G (independent cellular alarm path):

The DSC TL280E has its own dedicated cellular SIM. The 4G backup router SIM and the alarm panel SIM are separate and independent. The alarm panel cellular path is unaffected by whether the 4G backup router is functioning.

Pros:

  • Very low monthly cost ($15–$25/month vs $159/month for Starlink)
  • No upfront hardware cost beyond the router ($180–$250)
  • No sky-view obstruction concerns
  • TP-Link hardware matches existing ecosystem
  • Sufficient for the actual backup traffic load (alarm heartbeats, brief remote access)
  • No commercial use concerns — a plain data SIM has no use restrictions

Cons:

  • Coverage at Hamurana is unconfirmed — this option fails entirely if 4G signal is inadequate at the shed
  • Upload speeds variable and lower than Starlink — remote live-view quality during an outage will be lower
  • Rural 4G can itself be congested during peak hours
  • Requires coverage confirmation before commitment (site test or coverage map check)

Option C: No Backup — Phase 1 Risk Acceptance

What this means:

Accept that Lightwire is the sole internet path in Phase 1. If Lightwire is down, remote visibility is lost until it recovers. No backup hardware is purchased or configured.

Lightwire reliability context:

Lightwire claims 99.9%–99.99% uptime. For a rural fixed wireless tower serving a small area, 99.9% uptime equates to approximately 8.7 hours of unplanned outage per year. Lightwire's towers have backup power generation, reducing the risk of extended outages from local power cuts. Most outages are planned maintenance windows or weather-related path degradation — typically minutes to low hours.

Operational impact during a Lightwire outage:

SystemBehaviour during outageImpact
NVR / camerasContinues recording locally to on-site storageNone — footage preserved
Gate / access controlOperates on locally stored pin codes — customers can enter and exitNone
DSC TL280E alarm communicatorAutomatically fails over to cellular path for alarm signallingNone — alarm remains functional
Hik-Connect remote viewUnavailableEd/Tom cannot remotely check cameras
DSC Connect appAlarm notifications via cellular path continue — IP path notifications unavailableMinimal — cellular path handles alert delivery
Remote access control managementUnavailable (cannot add/remove pin codes remotely)Operational limitation during outage

Risk assessment for Phase 1:

The security-critical functions (alarm signalling, gate access, NVR recording) all continue independently during an internet outage. The only operational loss is remote visibility — Ed and Tom cannot view cameras or change access codes while the internet is down. For a low-traffic facility in Phase 1 with a small number of known customers, this is a manageable risk.

Pros:

  • Zero additional cost
  • Simplest possible network configuration
  • All security-critical functions remain operational during outages
  • Appropriate for Phase 1 where customer volume is low and customers are known contacts

Cons:

  • Remote visibility lost during outages (no camera view, no remote pin management)
  • If Lightwire goes down during an incident or security event, Ed/Tom cannot review footage remotely until it recovers
  • NVR local footage is available but requires physical access to review during an outage
  • Phase 2 upgrade to add backup will require re-visiting router configuration at that time (minor)

Phase 1 Recommendation: Option C (no backup) with Option B procurement research

Primary recommendation for Phase 1: Accept no backup connectivity at launch.

Rationale:

  1. The $3,000 Phase 1 internet budget is largely consumed by the cable run (conduit + labour ~$1,000) and will be further committed to Lightwire's 24-month contract (effectively a sunk monthly cost). There is no strong justification for adding $159/month (Starlink) or $180–250 hardware + $20/month (4G) to a backup link that protects only remote visibility — not any safety-critical function.
  1. All three safety-critical systems (alarm, gate access, NVR recording) are already designed to operate independently of internet connectivity. The compound requirements explicitly state that remote visibility loss during an outage is acceptable.
  1. Lightwire's claimed 99.9% uptime means less than 9 hours of unplanned outage per year at a facility with a small Phase 1 customer base. This is an acceptable risk.
  1. The ER706W has a second WAN port and USB port ready for backup connectivity to be added at any time in Phase 2 without hardware replacement.

Phase 2 recommendation: Option B (4G mobile backup)

Before Phase 2, carry out the following (see Open Questions):

  • Confirm 4G signal at the shed with a mobile phone (Spark and One NZ)
  • If signal is adequate (3+ bars in the shed or with an external antenna), deploy TP-Link MR6400 or similar on WAN2 with a Spark Business IoT SIM or One NZ equivalent
  • Total ongoing cost: Lightwire $139/month + 4G SIM $20/month = $159/month combined

This gives full redundancy for remote visibility at a fraction of Starlink's monthly cost, and is the right balance for a rural self-storage facility of this scale.

Starlink (Option A) is not recommended unless 4G coverage at the site proves inadequate. Starlink's $159/month ongoing cost is equal to the entire Lightwire primary plan cost, and is difficult to justify for a backup link that protects only remote visibility on a low-traffic Phase 1 site. Re-evaluate if the facility scales to Phase 3 with higher customer density and 24/7 remote management requirements.

Total monthly cost summary:

PhaseSetupMonthly cost (NZD incl. GST)
Phase 1Lightwire only$139/month
Phase 2 (recommended)Lightwire + 4G mobile backup~$159/month
Phase 2 (alternative, if no 4G coverage)Lightwire + Starlink$298/month

Network Configuration Recommendations

ER706W VLAN and Firewall Configuration

The compound requirements specify the following VLAN topology and this is appropriate for the hardware on hand:

VLAN 10 — Camera network

  • Members: NVR + all IP cameras (connected to TL-SG116P PoE+ ports assigned to VLAN 10)
  • Allowed outbound: Hik-Connect relay servers (TCP 80, 443, and Hik-Connect-specific ports — typically 8000, 8200, 554 for RTSP). Hikvision publishes their Hik-Connect server IP ranges; configure as destination address group.
  • Deny inbound from VLAN 20 (management)
  • Deny lateral movement: cameras should not be able to initiate connections to each other or to the NVR management interface from the camera VLAN (NVR has two NICs if applicable, or NVR management access is via VLAN 20 only)
  • No port forwarding to any camera or NVR — Hik-Connect P2P relay eliminates this requirement

VLAN 20 — Management network

  • Members: DSC TL280E alarm communicator, access control system, operator devices (Ed/Connor laptops when on-site)
  • Allowed outbound: DSC Connect cloud servers, access control cloud service (if applicable), general internet for management
  • Deny inbound from VLAN 10

Router hardening checklist:

  • Change default admin password on ER706W before deployment
  • Change default passwords on TL-SG116P switch
  • Change default passwords on all cameras and NVR
  • Disable UPnP on ER706W (Omada controller setting or web UI)
  • Disable remote management on ER706W unless VPN is configured
  • Enable logging on ER706W firewall rules (assists with incident investigation)

WAN failover configuration (when Phase 2 backup is added):

  • WAN1: Lightwire (via OS2 fibre → MC210CS → ER706W WAN1 SFP or ethernet port — confirm ER706W WAN port type)
  • WAN2: 4G router (ethernet from 4G router LAN port to ER706W WAN2)
  • Failover mode: NOT load balancing — configure as WAN1 primary, WAN2 failover only
  • Health check: configure ER706W to ping 8.8.8.8 and 1.1.1.1 on both WAN links; failover triggers when WAN1 health check fails

Easter 2026 Fibre Cable Run — Practical Notes

  • The OS2 fibre is pre-terminated LC-LC. Do not cut or strip the cable — it is plug-and-play.
  • Pull the fibre through conduit using a draw-wire with a fish-tape or rope attachment. Use a cable sock or pulling grip on the drum end, not taped to the connector. Do not exceed the rated pulling tension (typically 100–200N for single-mode fibre cable).
  • Minimum bend radius: OS2 single-mode typically 30mm installed, 15mm short-term during installation. Do not allow sharp bends at conduit entry points — use swept elbows or conduit bends, not sharp 90-degree elbow fittings.
  • Terminate at the house end: MC210CS media converter → SC port (via Dynamix LC-SC patch lead) → plugs into Lightwire router LAN port via ethernet (confirm which port on the Lightwire CPE — see Open Question 3).
  • Terminate at the shed end: OS2 LC directly into StarTech SFPGLCLHSMST SFP module seated in ER706W WAN or LAN SFP port.
  • Label both ends of the fibre at installation with permanent marker or cable labels: "OS2 FIBRE — HOUSE ↔ SHED — DO NOT BEND SHARPLY".
  • After installation, test with a simple ping from the shed router to the Lightwire CPE before burying/closing conduit penetrations.

Open Questions

The following items are unresolved and require action before or shortly after the Easter 2026 cable run:

  1. Lightwire peak-hour upload speed — Run a speed test (speedtest.net or fast.com) from the Lightwire connection at the house during peak hours (3pm–10pm on a weekday) to confirm upload is consistently at or above 3.5 Mbps under load. If upload drops below 3 Mbps at peak hours, discuss with Lightwire whether a plan upgrade or tower priority adjustment is available. This is the single most important pre-launch technical check.
  1. 4G/5G coverage at the shed — Spark and One NZ — Walk to the shed location with a Spark SIM and a One NZ SIM (or use coverage map tools at spark.co.nz/coveragemap and one.nz/coveragemap) and confirm signal strength. If 3+ bars of 4G are available inside or adjacent to the shed, Option B (4G backup) is viable for Phase 2 at low cost. Record the result and update this document.
  1. Lightwire CPE router model and LAN port — Confirm the model of the Lightwire CPE (customer premises equipment) router installed at the house. The MC210CS media converter connects to a LAN port on the Lightwire CPE via ethernet to extend the connection to the shed via fibre. Confirm which port should be used and whether the CPE supports gigabit ethernet on its LAN ports (the MC210CS is gigabit capable).
  1. Starlink commercial use terms — If Option A (Starlink) is revisited in Phase 2 or 3, verify whether the Residential Standard plan permits use at a commercial storage facility. If not, the Starlink Business plan (~$229/month NZD) would be required, further increasing the cost differential vs 4G backup.
  1. ER706W SFP port type for shed fibre termination — Confirm the ER706W has an SFP slot (it does — the ER706W includes 1x SFP WAN port) and that the StarTech SFPGLCLHSMST module is seated in that port, not in a copper LAN port. The OS2 LC fibre from the drum should connect directly to this SFP at the shed end.
  1. Lightwire fair use / peak-hour throttling policy — At plan activation, ask Lightwire to confirm in writing whether the Unlimited plan has any fair use policy, congestion management, or peak-hour speed shaping. This protects against unexpected upload throttling during evening hours when camera remote-view demand is highest.
  1. Alkathene conduit procurement — Purchase before Easter 2026. Farmlands Rotorua (Te Ngae Road) or RD1 Rotorua are the closest rural merchants. Phone ahead to confirm stock of 25mm x 100m rolls (two rolls needed for 200m run with a spare draw conduit).