Max Storage Limited

Te Waerenga Road, Hamurana — Project Hub — Target opening: late 2026

View Research →

Project Status

Security In Progress

Research done, no platform chosen. Estimates only, no vendor quotes. Phase 1 band $14,950-$23,000 incl. GST.

View research →
Infrastructure In Progress

Keep Lightwire; LTE signal test at the shed and peak upload test pending. Backup link only on a trigger.

View research →
Compliance In Progress

Fire, contract, insurance and signage researched. Contract awaits solicitor review. Loan covenants unconfirmed.

View research →
Operations In Progress

Storman Cloud plus Xero recommended. No Storman quote yet. Go-live and evidence-log continuity unconfirmed.

View research →
Consent In Progress

Non-notified discretionary consent planned for Oct/Nov 2026. Planning consultant not yet engaged.

View research →
Construction In Progress

Shed complete, gate installed. EasyGate keypad to be replaced in Phase 1; gate stays shut on power loss.

What Needs Doing Now

Current Assignments

Who is actively working on what. Update when tasks are completed, reassigned, or new work begins.

PersonTaskAreaExpected byNotes
JennyUpdate FMG insurance classification when usage changes to storage operationsInsuranceOngoingCurrent cover is $900/year as farm implements shed — update required before launch
EdGet written quotes for an integrated alarm and access system from an ICT Protege WX dealer and an Inner Range Inception dealerAccess control / AlarmsTBDPhase 1 (decided 2026-10-15). Ask each dealer in writing: no cap on PIN uses or hours, PIN expiry, a sample log export, re-arm 5 min after door close, panic opens the door. See source/research/security/recommendation.md
JennyProvide loan covenant documentsFinancialOngoingRequired before req-loan-covenants agent can produce meaningful output
EdResearch gate auto closureGateOngoingDecided 2026-10-15: the gate stays shut on power loss, with a manual release and a walk-through exit. EasyGate keypad is being replaced
TomRun the 4G signal test at the shed cabinet on Spark and One NZInfrastructureTBDThe alarm's backup path depends on it. Test method in working/internet/source-internet.md
TomNote the gate motor model and the gate-to-cabinet distanceAccess controlTBDDecides Cat6 versus fibre to the gate. Boat bay openers are confirmed as Grifco LS-Drive with battery backup (2026-10-15)
TomCheck the Grifco LS-Drive installation manual for a wired push-button or access-control input, and for how long the battery backup lasts in a power cutAccess controlTBDThe new access controller and panic button open the door through that input. Not confirmed online

Waiting On

ItemWaiting onWho is chasingSinceAction when receivedStatus
Loan covenant documentsJennyTom2026-03-20Provide to req-loan-covenants agent; run /refresh-base-knowledge loan-covenantsOPEN
Intercompany lease — accountant advice on structureAccountantEd/Jenny2026-03-31Provide to req-intercompany agent; run /refresh-base-knowledge intercompanyOPEN
Planning consultant engagementTBDEd2026-08-01 (target)Run /generate-consent-plan incorporating consultant guidance once engagedOPEN

Recent Decisions

DateDomainDecisionRationaleWho decidedWhat this locks in
2026-03-31InternetRun fibre cable from house to shed — Easter 2026 (~18 Apr)Required for camera system and remote access controlEdCable route must be confirmed on Easter visit; Lightwire primary provider
2026-04-01InsuranceBuilding insured with FMG at $900/year as 'farm implements' shedFMG requires building complete before insuring; building now completeJenny (via FMG)Current cover is provisional — Jenny must update FMG when usage changes to storage operations
2025-08-21Farm leaseTom to pursue leasing the Te Waerenga Road farm to the neighbour across the road, on terms that cover rates and retain Douglas Enterprises' right to use the landJenny unable to farm it herself; known trustworthy neighbour; farm lease may also bring early storage customersTom, EdTom to follow up with Jenny directly; farm lease supports the 40% agricultural use requirement for resource consent
2025-08-21Customer contents insuranceStorage customers are responsible for insuring their own contents; Max Storage insures building only; optional contents cover may be offered as an add-on arranged through Max StorageIndustry norm; limits operator liability for customer goodsEdMust be reflected in customer contract terms; operator liability clause to exclude customer goods
2026-10-15Access controlReplace the EasyGate keypad in Phase 1 with access control that has no cap on PIN life, is remotely programmable, logs every entry and exit, and disarms the alarm on a valid PINEasyGate temporary PINs are capped at 255 entries/exits or 255 hours; it has no log and no remote managementEdThe EasyGate stays only until the replacement is installed; the access controller and alarm panel must be chosen together
2026-10-15AlarmsInstall the alarm in Phase 1, integrated with access control. It re-arms about 5 min after the shed door closes, with an inside panic button and free exitBoats stored on site; a person shut inside must be able to get out without setting off the alarmEdThe alarm moves from Phase 2 to Phase 1; check the budget; check the panic and exit design against Building Code means-of-escape
2026-10-15Security scopeOnly the 6 boat bays (11m x 4m) get keypads and the alarm. The 6 small bays (4m x 4m) use the client's own padlockBoats are the high-value stock; small bays are padlock-onlyEdAlarm partitions and readers sized for 6 bays plus common areas
2026-10-15Security safetyThe inside panic button unlocks and opens the boat bay door. The person closes it themselvesA person shut inside must be able to get outEdPanic button wired to the door opener and the alarm; check the building warrant of fitness impact with the council
2026-10-15Access controlThe gate stays shut on power loss. It has a manual release and a separate walk-through exitSecurity of a site with nobody on itEdGate hardware must be fail-secure, with a manual override
2026-10-15Site factsThe boat bay roller doors use Grifco LS-Drive openers with Battery Backup (BBU)Confirmed by EdEdPanic-open works in a power cut through the opener's own battery. The access controller must drive the LS-Drive's control input

Site Features Under Consideration

Site Features — Options and Considerations

Physical site features that are under consideration but not yet decided. Each entry captures the design options and key constraints so decisions can be made when ready.


Road Visibility of Outdoor Storage Area

The site has very low visibility from Te Waerenga Road. RVs, boats on trailers, caravans, and vehicles stored in the outdoor area are substantially invisible from the road.

Planning implication: This materially reduces the visual impact adverse effects that are typically the primary challenge for outdoor vehicle storage consent in a rural zone. The key non-notification risk factor — large vessels visible from the road — is significantly mitigated. The non-notification likelihood for outdoor storage is therefore higher than the generic rural zone assessment suggests.

How to apply: When assessing planning/consent risk for outdoor storage, the visual impact from the road should be treated as low. The relevant sightline risk is from neighbouring dwellings, not from Te Waerenga Road. The AEE visual effects section should focus on screening relative to neighbouring properties, not road visibility.


Washdown Facility (Hose/Water Point)

A water hose point to allow customers to wash down boats, vehicles, or equipment.

Key constraint: The site is on tank water. Unattended hose flow is a real operational risk — someone leaving it running could empty the tank.

Decision status: Not yet decided whether to include this feature at all.

Shut-off options (if washdown proceeds):

OptionHow it worksApprox. cost (NZD)Notes
Hose bib timer (mechanical)Spring-wound timer on tap; customer sets duration (5–30 min)$30–80No power needed; customer can reset timer
Push-button timed solenoidButton activates flow for a fixed period (e.g., 10 min) then auto-cuts$100–300 (components)Reliable; no customer override
Flow-meter shut-offCuts off after a preset volume (e.g., 200 L) regardless of time$150–400More precise than time-based
Low-tank level sensor + cutoffFloat switch or ultrasonic sensor shuts solenoid when tank drops below set level$50–150Belt-and-braces failsafe at tank level

Recommended approach: Push-button timed solenoid (10-min cycles) as primary control, plus a low-tank level sensor as a failsafe at the tank. NZ sourcing: RD1, Farmlands, Irrigation Warehouse.