Max Storage Limited
Te Waerenga Road, Hamurana — Project Hub — Target opening: late 2026
View Research →Project Status
Research done, no platform chosen. Estimates only, no vendor quotes. Phase 1 band $14,950-$23,000 incl. GST.
View research →Keep Lightwire; LTE signal test at the shed and peak upload test pending. Backup link only on a trigger.
View research →Fire, contract, insurance and signage researched. Contract awaits solicitor review. Loan covenants unconfirmed.
View research →Storman Cloud plus Xero recommended. No Storman quote yet. Go-live and evidence-log continuity unconfirmed.
View research →Non-notified discretionary consent planned for Oct/Nov 2026. Planning consultant not yet engaged.
View research →Shed complete, gate installed. EasyGate keypad to be replaced in Phase 1; gate stays shut on power loss.
What Needs Doing Now
Current Assignments
Who is actively working on what. Update when tasks are completed, reassigned, or new work begins.
| Person | Task | Area | Expected by | Notes |
|---|---|---|---|---|
| Jenny | Update FMG insurance classification when usage changes to storage operations | Insurance | Ongoing | Current cover is $900/year as farm implements shed — update required before launch |
| Ed | Get written quotes for an integrated alarm and access system from an ICT Protege WX dealer and an Inner Range Inception dealer | Access control / Alarms | TBD | Phase 1 (decided 2026-10-15). Ask each dealer in writing: no cap on PIN uses or hours, PIN expiry, a sample log export, re-arm 5 min after door close, panic opens the door. See source/research/security/recommendation.md |
| Jenny | Provide loan covenant documents | Financial | Ongoing | Required before req-loan-covenants agent can produce meaningful output |
| Ed | Research gate auto closure | Gate | Ongoing | Decided 2026-10-15: the gate stays shut on power loss, with a manual release and a walk-through exit. EasyGate keypad is being replaced |
| Tom | Run the 4G signal test at the shed cabinet on Spark and One NZ | Infrastructure | TBD | The alarm's backup path depends on it. Test method in working/internet/source-internet.md |
| Tom | Note the gate motor model and the gate-to-cabinet distance | Access control | TBD | Decides Cat6 versus fibre to the gate. Boat bay openers are confirmed as Grifco LS-Drive with battery backup (2026-10-15) |
| Tom | Check the Grifco LS-Drive installation manual for a wired push-button or access-control input, and for how long the battery backup lasts in a power cut | Access control | TBD | The new access controller and panic button open the door through that input. Not confirmed online |
Waiting On
| Item | Waiting on | Who is chasing | Since | Action when received | Status |
|---|---|---|---|---|---|
| Loan covenant documents | Jenny | Tom | 2026-03-20 | Provide to req-loan-covenants agent; run /refresh-base-knowledge loan-covenants | OPEN |
| Intercompany lease — accountant advice on structure | Accountant | Ed/Jenny | 2026-03-31 | Provide to req-intercompany agent; run /refresh-base-knowledge intercompany | OPEN |
| Planning consultant engagement | TBD | Ed | 2026-08-01 (target) | Run /generate-consent-plan incorporating consultant guidance once engaged | OPEN |
Recent Decisions
| Date | Domain | Decision | Rationale | Who decided | What this locks in |
|---|---|---|---|---|---|
| 2026-03-31 | Internet | Run fibre cable from house to shed — Easter 2026 (~18 Apr) | Required for camera system and remote access control | Ed | Cable route must be confirmed on Easter visit; Lightwire primary provider |
| 2026-04-01 | Insurance | Building insured with FMG at $900/year as 'farm implements' shed | FMG requires building complete before insuring; building now complete | Jenny (via FMG) | Current cover is provisional — Jenny must update FMG when usage changes to storage operations |
| 2025-08-21 | Farm lease | Tom to pursue leasing the Te Waerenga Road farm to the neighbour across the road, on terms that cover rates and retain Douglas Enterprises' right to use the land | Jenny unable to farm it herself; known trustworthy neighbour; farm lease may also bring early storage customers | Tom, Ed | Tom to follow up with Jenny directly; farm lease supports the 40% agricultural use requirement for resource consent |
| 2025-08-21 | Customer contents insurance | Storage customers are responsible for insuring their own contents; Max Storage insures building only; optional contents cover may be offered as an add-on arranged through Max Storage | Industry norm; limits operator liability for customer goods | Ed | Must be reflected in customer contract terms; operator liability clause to exclude customer goods |
| 2026-10-15 | Access control | Replace the EasyGate keypad in Phase 1 with access control that has no cap on PIN life, is remotely programmable, logs every entry and exit, and disarms the alarm on a valid PIN | EasyGate temporary PINs are capped at 255 entries/exits or 255 hours; it has no log and no remote management | Ed | The EasyGate stays only until the replacement is installed; the access controller and alarm panel must be chosen together |
| 2026-10-15 | Alarms | Install the alarm in Phase 1, integrated with access control. It re-arms about 5 min after the shed door closes, with an inside panic button and free exit | Boats stored on site; a person shut inside must be able to get out without setting off the alarm | Ed | The alarm moves from Phase 2 to Phase 1; check the budget; check the panic and exit design against Building Code means-of-escape |
| 2026-10-15 | Security scope | Only the 6 boat bays (11m x 4m) get keypads and the alarm. The 6 small bays (4m x 4m) use the client's own padlock | Boats are the high-value stock; small bays are padlock-only | Ed | Alarm partitions and readers sized for 6 bays plus common areas |
| 2026-10-15 | Security safety | The inside panic button unlocks and opens the boat bay door. The person closes it themselves | A person shut inside must be able to get out | Ed | Panic button wired to the door opener and the alarm; check the building warrant of fitness impact with the council |
| 2026-10-15 | Access control | The gate stays shut on power loss. It has a manual release and a separate walk-through exit | Security of a site with nobody on it | Ed | Gate hardware must be fail-secure, with a manual override |
| 2026-10-15 | Site facts | The boat bay roller doors use Grifco LS-Drive openers with Battery Backup (BBU) | Confirmed by Ed | Ed | Panic-open works in a power cut through the opener's own battery. The access controller must drive the LS-Drive's control input |
Site Features Under Consideration
Site Features — Options and Considerations
Physical site features that are under consideration but not yet decided. Each entry captures the design options and key constraints so decisions can be made when ready.
Road Visibility of Outdoor Storage Area
The site has very low visibility from Te Waerenga Road. RVs, boats on trailers, caravans, and vehicles stored in the outdoor area are substantially invisible from the road.
Planning implication: This materially reduces the visual impact adverse effects that are typically the primary challenge for outdoor vehicle storage consent in a rural zone. The key non-notification risk factor — large vessels visible from the road — is significantly mitigated. The non-notification likelihood for outdoor storage is therefore higher than the generic rural zone assessment suggests.
How to apply: When assessing planning/consent risk for outdoor storage, the visual impact from the road should be treated as low. The relevant sightline risk is from neighbouring dwellings, not from Te Waerenga Road. The AEE visual effects section should focus on screening relative to neighbouring properties, not road visibility.
Washdown Facility (Hose/Water Point)
A water hose point to allow customers to wash down boats, vehicles, or equipment.
Key constraint: The site is on tank water. Unattended hose flow is a real operational risk — someone leaving it running could empty the tank.
Decision status: Not yet decided whether to include this feature at all.
Shut-off options (if washdown proceeds):
| Option | How it works | Approx. cost (NZD) | Notes |
|---|---|---|---|
| Hose bib timer (mechanical) | Spring-wound timer on tap; customer sets duration (5–30 min) | $30–80 | No power needed; customer can reset timer |
| Push-button timed solenoid | Button activates flow for a fixed period (e.g., 10 min) then auto-cuts | $100–300 (components) | Reliable; no customer override |
| Flow-meter shut-off | Cuts off after a preset volume (e.g., 200 L) regardless of time | $150–400 | More precise than time-based |
| Low-tank level sensor + cutoff | Float switch or ultrasonic sensor shuts solenoid when tank drops below set level | $50–150 | Belt-and-braces failsafe at tank level |
Recommended approach: Push-button timed solenoid (10-min cycles) as primary control, plus a low-tank level sensor as a failsafe at the tank. NZ sourcing: RD1, Farmlands, Irrigation Warehouse.