Storage Business Action Plan

πŸ“… Current Situation

Building Contract:Totalspan 24m x 15m x 4.8m shedβœ… Signed March 27, 2025
Total Cost:$327,415.35Deposit paid: $10,000
Timeline:2-4 weeks post-consent12-16 weeks completion
Ground Prep:Remedial work for "good ground"βœ… Completed
Financial:$470,000 debt @ 6.2%Interest covered by rentals

πŸ’΅ Payment Schedule

Milestone Amount Status
Deposit$10,000βœ… Paid
Upon Council Consent$113,043.48⏳ Pending
Upon Completion of Slab$86,956.52⏳ Future
Upon Commencement of Construction$69,555.22⏳ Future
Final Payment (7 days after completion)$6,447.83⏳ Future

🎯 Priority Phases

Phase 1: Immediate Actions (Next 2 Weeks)

TaskAction RequiredPriority
Track Building ConsentContact Totalspan weeklyπŸ”΄ Critical
Prepare Foundation100mm concrete slab with steel reinforcementπŸ”΄ Critical
Site PreparationClear 2.5m outside + 4m vehicle clearanceπŸ”΄ Critical
Document ProgressWeekly photos showing "agricultural facility"🟑 Important

Phase 2: Pre-Construction (Weeks 3-4)

  • Create customer tracking spreadsheet
  • Open Square/Stripe account
  • Design outdoor space numbering
  • Build waiting list from neighbors
  • Create rental agreement template

Phase 3: During Construction (Weeks 5-16)

  • Install gate keypad ($800)
  • Number outdoor spaces
  • Move farm equipment
  • Install basic security

Phase 4: Launch Operations (Months 4-5)

Storage TypeQuantityPrice/MonthRevenue Target
Boat Spaces10$200$2,000
Caravan Spaces10$160$1,600
Car/Trailer20$100$2,000
Indoor Bays5-7$400-500$2,000+
Total Initial Target$7,600/month

πŸ—ΊοΈ 6-Month Roadmap

MonthFocusRevenue TargetCustomer TargetKey Actions
Month 1 Launch outdoor storage $2,000 5-10 Start immediately, install keypad, document everything
Month 2 Growth & systemization $3,000 15-20 Facebook marketing, neighbor outreach
Month 3 Technology upgrade $4,000 20-25 Consider 6Storage, automate invoicing
Months 4-6 Build consent evidence $5,000/mo 30-40 Pin pad data, photo documentation
Month 7 Submit consent - - Hire consultant, submit application

⚠️ Risk Mitigation

RiskProbabilityImpactMitigation
Construction DelaysMediumLowStart outdoor storage regardless
Consent RejectionLow (10-20%)MediumBuild 6-month operational history first
Slow Customer UptakeLowMediumFacebook ads + competitive pricing
Weather DelaysMediumLowFocus on indoor marketing
CompetitionLowLowSuperior location and facilities

🎯 Success Targets

TimeframeRevenue TargetCustomer TargetOccupancyKey Milestone
Year 1$45,0005040%Establish operation
Year 2$70,0007060%Growth phase
Year 3$93,0008580%Optimization
Year 5$104,00010090%Plan Shed #2
Year 10$250,000200+95%$2M property value

βœ… Critical Success Factors

DO These Things:

  • Start outdoor storage immediately
  • Document EVERYTHING with photos
  • Install pin pad in Month 1
  • Keep 40% of shed for farm equipment
  • Frame as "agricultural equipment storage"
  • Build neighbor support with discounts
  • Track every metric from Day 1

NEVER Do These:

  • Don't call it "self-storage"
  • Don't rush consent without evidence
  • Don't ignore documentation
  • Don't price too high initially
  • Don't neglect neighbor relationships
  • Don't forget agricultural positioning