Construction Progress Tracker

Te Waerenga Road Storage Facility - Real-time construction status

πŸ“Š Overall Progress: 35% Complete

35%

Current Status Summary

Component Status Completion Notes
Council Consent βœ… APPROVED 100% Complete - can proceed
Concrete Slab βœ… COMPLETE 100% Complete with extended southern footings
Building Kitset βœ… DELIVERED 100% Delivered to site - ready for construction
External Fence 🟑 IN PROGRESS 85% Needs metal base & gate
Shed Construction ⏳ NOT STARTED 0% Ready to begin - kitset on site

πŸ’° Payment Tracker

Payment Amount Status Trigger
Deposit $10,000 βœ… PAID Contract signing
Council Consent $113,043.48 βœ… PAID Consent approval
Slab Completion $100,920.00 πŸ“§ INVOICED Sep 1 Invoice #4532 (includes extended footings)
Water Pipe Installation $373.75 πŸ“§ INVOICED Aug 27 Invoice #5846 from Andersen Civil
Construction Start $69,555.22 ⏳ PENDING When building starts
Final Payment $6,447.83 ⏳ PENDING 7 days after completion
Outstanding Invoices $101,293.75 Payment Due
Total Remaining Contract $76,003.05

πŸ“… Upcoming Milestones

  • September 1, 2025: βœ… Slab complete, kitset delivered
  • Outstanding: Invoice payments totaling $101,293.75
  • Mid-September: Begin shed construction, payment $69,555.22
  • Late September: Complete shed erection
  • October 2025: Final inspection and opening