Te Waerenga Road Storage Facility - Real-time construction status
| Component | Status | Completion | Notes |
|---|---|---|---|
| Council Consent | β APPROVED | 100% | Complete - can proceed |
| Concrete Slab | β COMPLETE | 100% | Complete with extended southern footings |
| Building Kitset | β DELIVERED | 100% | Delivered to site - ready for construction |
| External Fence | π‘ IN PROGRESS | 85% | Needs metal base & gate |
| Shed Construction | β³ NOT STARTED | 0% | Ready to begin - kitset on site |
| Payment | Amount | Status | Trigger |
|---|---|---|---|
| Deposit | $10,000 | β PAID | Contract signing |
| Council Consent | $113,043.48 | β PAID | Consent approval |
| Slab Completion | $100,920.00 | π§ INVOICED Sep 1 | Invoice #4532 (includes extended footings) |
| Water Pipe Installation | $373.75 | π§ INVOICED Aug 27 | Invoice #5846 from Andersen Civil |
| Construction Start | $69,555.22 | β³ PENDING | When building starts |
| Final Payment | $6,447.83 | β³ PENDING | 7 days after completion |
| Outstanding Invoices | $101,293.75 | Payment Due | |
| Total Remaining Contract | $76,003.05 | ||