Master Plan - Max Storage Limited

Your comprehensive command center for the storage facility project

πŸ“Š Current Reality Check

Construction Status (August 2025)

Component Status Timeline Dependencies
Concrete Slab βœ… COMPLETE Poured Aug 19, 2025 Now curing (7-14 days)
Fence 85% Complete Few days Metal base & gate installation
Shed Construction Not Started 3-4 weeks after slab Slab must cure 7-14 days first
Total Completion 35% Overall 8-12 weeks Weather is main variable

πŸ—“οΈ Integrated Project Timeline

Phase 0: Construction Completion (Now - Oct/Nov 2025)

Construction Tasks

  • Monitor concrete curing
  • Coordinate with Totalspan
  • Complete fence and gate
  • Pay milestones: $86,956 + $69,555

Business Setup

  • Bank account (accountant handling)
  • IRD/GST registration
  • Pin pad research ($3,200-4,800)
  • Customer tracking system

Pricing Strategy

Large Units (48mΒ² - 4m Γ— 12m):

  • Launch: $95/week
  • Standard: $110/week
  • Premium: $125/week

Small Units (12mΒ² - 4m Γ— 3m):

  • Launch: $35/week
  • Standard: $40/week
  • Premium: $45/week

Outdoor Storage:

  • Small: $35-45/week
  • Large: $70-85/week

Phase 1: Soft Launch - "Agricultural Storage" (Months 1-6)

Component Implementation Cost Purpose
Access Control Basic pin pad at gate $800-1,500 Track access, prove low impact
Security Solar lights, trail cameras $500-1,000 Basic deterrent
Management Excel + Square/Stripe $10-30/month Simple tracking

Target Revenue: $5,850-7,650/month (6 large units @ $95-125/week + 6 small units @ $35-45/week + 10-15 outdoor spaces)

Phase 2: Building Credibility (Months 6-12)

  • Security Upgrade: Connected keypad, 4-camera system ($3,000-5,000)
  • Software Decision: Evaluate 6Storage at 20+ customers
  • Marketing Expansion: Facebook, Google My Business ($500-1,000)
  • Consent Application: Use 6 months of data ($5-10k for consultant)

Target Revenue: $7,950-10,400/month (12 units + outdoor storage at full occupancy)

🎯 Key Decision Points

Immediate

  • Pin pad: Basic ($800) vs Connected ($1,500-2,000)
  • Insurance: FMG vs alternatives
  • Launch price: $95 vs $110

Month 1-3

  • Camera system selection
  • Payment processing setup
  • Marketing approach

Month 3-6

  • Software upgrade timing
  • Consent strategy
  • Expansion planning

πŸ“š Related Planning Documents

Strategic Roadmap

5-year vision and expansion strategy

View Roadmap

Construction Progress

Detailed construction tracker and timeline

View Progress

Consent Strategy

Regulatory compliance and approval path

View Strategy